Sturgis Water System Improvements
Overview of Phase I and II
Update November 1, 2012...
Both the Phase 2 Water Main Replacement project and the Lazelle Street Water Main Project are in the final stages.  Asphalt is being installed and remining concrete work fiished.  Lazelle Street is expected to be re-opened for traffic no later than November 6, 2012 and will remain open unti early spring when theproject resumes.

Summary of Phase I and II (presentation)


Phase I
general Contractor - Mainline Contracting Inc.
Contract Price $909,139.50
Start Date:  September 19, 2011
Final Completion Date: June 29, 2012

Phase I includes making upgrades to several 4" water mains and lines in the city.
Replace Glover Street main from Junction to Fulton
Replace Marshall Street mains from Fulton to Baldwin
Replace Baldwin Street mains from Marshall to Harmon
Replace Fulton Street mains from Harmon to Channel
Replace Davenport mains from Park to Marshall

As of January 2012, most of phase I has been complete

For more information related to the Sturgis Water System Improvements, contact the Municipal Utility Department at 605-347-4425.

Plans


Phase II
Includes replacement of well 1
Upgrades to well 3
Replace Spruce Street main

Phase II will begin the week of June 25, 2012 with work on Spruce Street.  Phase II will also include the Lazelle Street water line upgrade and main replacement project.  (see Lazelle Street Project page for information)