Moose Drive Improvements
Update:
6/18/2012 Project is complete.
3/26/2011 Crews will be installing guardrail this week near the west end of the street.
Moose Drive Reconstruction Bid Opening March 8, 2012.
- Received 6 bids ranging from $242,212.50 to $343,968.10
- Low Bidder was Johner & Sons @ $242,212.50
- Engineers Estimate was $268,922.00, resulting in a $26,709.50 savings over the estimate
About the Project:
Contractors will be making significant repairs to Moose Drive including repaving portions of the surface and installing guardrail.
The project will begin in mid-April (depending on weather) and is scheduled to be finished by the end of July.
|
|